May 2007
|
Patio base constructed together with the outside bathroom |
April 2007
|
Preparation for Patio area complete |
|
Internal floor tiling completed |
March 2007
|
Main Bedroom stone facade completed and preparation of the external area for patio and outside Bathroom |
|
Preparation for Path around the building |
|
Stone facade to Main bedroom |
February 2007
|
End of February external view |
|
Lounge ceiling before sand blasting and re-pointing |
|
Lounge ceiling after sand blasting and re-pointing |
|
Topping off the trulli cone |
December 2006
|
The builder’s work is nearing completion, now the internal electrical and plumbing work can commence. Also the doors and windows are currently being hand made. |
|
View on the roof, showing the terracing |
November 2006
|
View over the swimming pool |